How long will your first AI project take?

Separate the work from the waiting time with an illustrative schedule, and see which questions to ask before accepting a project date.

A saved prompt for a task you already understand and a tool connected to several business systems have very different schedules. Ask what the proposed date includes before treating it as the date the team can use the result.

You need enough time to prepare the material, try the approach on suitable work and decide what the results mean. The supplier’s setup estimate may cover some of that, or none of it.

Build the schedule from the actual work

Suppose a business wants a shared tool for drafting answers from its product information. This hypothetical schedule shows how the pieces could fit together:

Stage

Illustrative duration

What must be ready

Agree the task and limits

One week

Someone who understands the enquiries

Prepare current source material

Two weeks

Time from the people responsible for it

Configure the drafting tool

One week, alongside preparation

Approved account and access

Test and decide

Two weeks

Source material and reviewer time

Introduce to the team

One week

Useful results, instructions and support

With setup running alongside preparation, this example takes six weeks. Those durations are assumptions, not typical delivery times. Existing documents could reduce preparation; an unresolved permission or integration issue could extend it.

Count hours and calendar time separately

If preparing the documents needs twelve hours and the person doing it can spare three hours a week, allow roughly four weeks. Writing “twelve hours” in the plan without checking availability hides most of the delay.

Also check who is doing several jobs. The same person may prepare the documents, check the drafts and answer questions during introduction. Their total workload matters more than the apparent simplicity of any one step.

For each uncertain stage, ask what could make the estimate change. A test may reveal that the material does not answer common questions. Record the extra work and revise the date when that happens.

Questions for the supplier

  • What will be working at the end of your estimate?
  • What do you expect us to provide, and by when?
  • Does the estimate include testing, corrections and staff introduction?
  • Which access approvals or other systems could delay the work?
  • What happens if the trial shows the approach is unsuitable?

An estimate with those answers is more useful than a confident date on its own. Use the staff-hours in the cost estimate, and use the dependencies and availability to set the calendar.

Jay Janes

About Jay

I’m Jay Janes, a Practical AI Advisor and founder of Reformat Labs. I write about choosing useful work for AI, checking the results and supporting the people using it.

Contact

Talk to Jay

Considering AI for a task in your business? Tell me what takes too long, causes problems or needs to improve.

What to send

For advice or a workshop, describe the work and your question. For a talk or podcast, send the audience, subject and date.